This is only a preview of the October 2025 issue of Silicon Chip. You can view 34 of the 104 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Items relevant to "Digital Preamp & Crossover":
Items relevant to "HomeAssistant, Part 2":
Items relevant to "Vacuum Controller":
Items relevant to "Dual Train Controller":
Articles in this series:
Purchase a printed copy of this issue for $14.00. |
This Vacuum Controller switches
on a vacuum when an appliance
such as a circular saw is started.
It runs the vacuum for a preset
period after the appliance
is switched off to draw up
remaining dust. It includes
optional blast gate control, and
interlinking between units, for
use with more than one tool.
John Clarke’s
Vacuum Cont
V
acuuming up dust produced by
woodworking machinery is a
necessity for cleanliness, safety
and health reasons. Manufactured
and natural timber dust can be toxic
or become an irritant to the lungs if
breathed in, ultimately causing health
problems. Dust from timbers such as
western red cedar can increase the risk
of developing throat cancer.
Wearing a face mask limits the
amount of dust entering the lungs.
However, fine dust in the air can also
become an explosion hazard. Ideally,
this dust should be vacuumed up as
it is produced, to minimise airborne
wood particle dust. Besides, who
wants to clean up a workshop full of
sawdust after doing some work?
Incidentally, vacuuming air through
ducting tubes made from metal or plastic can cause an electrostatic charge
to build. If not Earthed, the charge
buildup can produce sparks, resulting
in dust explosions.
It is important to provide Earthing
for metal ducting and include Earthed
bare wires within any plastic pipes
to prevent this (see siliconchip.au/
link/ac71).
Major dust producers include circular saws, thicknessers and routers.
Where there is more than one appliance, you would typically have a single vacuum unit, with ducting between
54
Silicon Chip
them. A valve in the ducting at each
appliance, called a ‘blast gate’, can
be opened or closed for the vacuum
to draw dust only from the appliance
concerned (otherwise, the suction
would be too weak).
With our Vacuum Controller, the
operation of the vacuum and blast
gates is fully automatic. Switch on
your appliance, and the vacuum will
automatically start and run for as long
as the appliance is running. Then,
once the appliance is switched off,
the vacuum will continue to run for a
preset period.
Blast gate control can be automated
provided the blast gates are electrically operated by actuators or solenoids. Solenoids use an electromagnet that pulls in a plunger whenever
the solenoid is powered. A spring is
used to return the plunger to its resting position when power is off. An
actuator is essentially a DC electric
motor that drives a rod out or in using
a worm gear.
If you are not familiar with actuators, you can see an example of one at
siliconchip.au/link/ac72
When used with the Vacuum Controller, the blast gate associated with
the powered on appliance is opened.
The appliance or appliances that are
not operating will have their blast
gates closed.
Australia's electronics magazine
A woodworking workshop setup for
removing dust is not a topic that we
will investigate in detail here. There
is much detailed information on it at
siliconchip.au/link/ac73 and other
reputable websites on the topic.
Presentation
Our Vacuum Controller can be built
to suit your workshop. Its most basic
form is a single Vacuum Controller
unit that switches a vacuum for a single appliance. The Vacuum Controller
detects when its appliance is running
and powers the vacuum. We call this
Vacuum Controller the master unit.
It is the only unit that contains the
switching components for the vacuum.
The optional blast gate control can
be connected to this unit. This provides relay contacts to enable control
of a solenoid or actuator to open or
close the blast gate. It is connected via
an 8P8C RJ-45 connector that allows
standard Cat 5/Cat 6 leads to be used.
You can use a different connector
should more current be required (more
on that later).
For each appliance after the first,
you will need another partially populated Vacuum Controller board. These
extra units don’t include the switching
components for the vacuum, as they
are connected back to the main unit.
This interlinking allows any of the
siliconchip.com.au
Appliance & vacuum ratings: up to 10A at 230V AC
Appliance on-detection threshold: 166mA (~40W)
Vacuum run time after appliance is off: adjustable
from half a second to 30s
Blast gate opening and closing time
compensation: 0-7.5s
Vacuum wind-down period compensation: 0-7.5s
Can be used with a single appliance or multiple
appliances via interlink connections
Optional blast gate control option for each
appliance; it opens for the appliance being used
Cat 5/6 or telephone cables for interlinking &
blast gate control
Fully automatic operation plus manual operation
for vacuum and blast gate
Power, vacuum and blast gate indicators
troller
interconnected Vacuum Controllers to
control the action of the vacuum via
the master unit.
When a Vacuum Controller unit
detects that its connected appliance
is on, the master unit is signalled to
switch on the vacuum.
If using blast gates, there are two
possible control methods that can be
selected. The default is to only open
the blast gate for the currently operating appliance. The other option will
keep the blast gate open for the last
used appliance. This gate will close
when a different appliance starts.
Fig.1 shows, as an example, the
arrangement of three interlinked units.
Interconnection is via RJ-10 4P4C
sockets and 4-wire telephone style
cabling with RJ-10 plugs for an easy
interconnection system.
For Home workshops
The master unit includes two mains
inputs and two mains outlets (General
Purpose Outlets [GPO]). These are to
supply the appliance and the vacuum
independently. Each mains input
must plug into a separate mains outlet to allow for up to 10A <at> 230V AC
(2300VA) to be drawn from each. Circular saws can be rated at 1800VA or
more and vacuums at around 1200VA,
so it is not feasible to run both from
the one 10A mains outlet.
The mains supply for the appliance is directly connected between
the input and output via a current
transformer inside the Vacuum Controller unit. This current transformer
is used to monitor the appliance current. When current is detected, it
indicates to the Vacuum Controller
that the appliance is running and so
switches on the vacuum via the second
mains output. Power for the vacuum
is switched using a heavy duty relay.
If more than one Vacuum Controller
is built, subsequent units only require
one mains power input and one mains
outlet for that unit’s connected appliance. The vacuum is only switched on
and off via the master unit, which is
signalled to switch via the interlinking
connection between units.
If blast gate control is installed,
interlinking sets the blast gate open
for the appliance that is running and
closes the blast gates for those units
that do not have their associated appliance running.
There is the option to have the blast
gate for the last running appliance kept
open after the appliance is switched
off. This speeds up switching on the
Left: the Blast Gate Control Adaptor is
a simple PCB that can be built to convert RJ-45 8P8C (eight position/eight conductor) connections to screw terminals.
Right: the Vacuum Pump Controller has two 230V 10A power outlets for supplying the appliance and vacuum.
siliconchip.com.au
Australia's electronics magazine
October 2025 55
vacuum if you use the same tool again.
When the blast gate is closed, it needs
to wait for the blast gate to open before
the vacuum is started. If the blast gate
is already open, the vacuum can start
immediately.
LED indicators are included on each
for power, vacuum running and blast
gate open. Two momentary pushbutton
switches provide manual control of the
vacuum and the blast gate. The blast
gate LED, associated switch and other
blast gate related components can be
left off if you don’t need this feature.
Also, the interlinking components
are not necessary if you only intend
to build one master unit.
One or two additional units can be
connected to the master unit and be
powered from it. The master unit has
a mains transformer to power itself,
and the resulting 12V is supplied to
other units via the interlink connections. If more than three units are
required, then the fourth unit will
need to include another power transformer. This allows for up to six to be
connected in total.
Because the Vacuum Controller can
be built with several options, the circuit and PCB overlay diagrams show
the separate sections of the circuit,
some of which may not be required in
each unit. Similarly, the parts list separates out the parts for each section.
Timers and operation
Three timers are used in the operating logic: the vacuum timer, blast gate
operating period timer and the vacuum
wind-down timer.
The vacuum timer sets the period
for which the vacuum runs after the
appliance is switched off. This can
56
Silicon Chip
be adjusted from 0-30s. The blast gate
timer should be set to the time taken
for the blast gate to open or close,
allowing the blast gate to be fully
open before the vacuum is started. It
prevents damage to the vacuum pipe
work and blast gates if all blast gates
are closed when the vacuum starts.
The blast gate timeout can be set
up to 7.5s. If blast gate control is not
used, it can be set to zero, for no delay
in starting.
The vacuum wind-down timer is
included so that the blast gate does
not close until the vacuum motor has
stopped after being switched off. It can
be set for up to 7.5s, preventing excessive vacuum pressure by keeping the
blast gate open while the vacuum is
spinning down due to inertia.
The Vacuum Controller is initially
in a waiting state until either its connected appliance is switched on, or
the interlink signal indicates that the
appliance connected to another unit
is switched on. As long as neither are
on, it continues to wait.
When the connected appliance
switches on, the blast gate is powered on if it isn’t already open. The
blast gate LED flashes during the
opening period (this is skipped if it
was already open). The interlink signal then becomes active. At the same
time, the vacuum motor and its indicator LED are switched on.
After the appliance is switched off,
the vacuum timer starts. When it ends,
the vacuum is switched off, along with
the interlink signal.
If JP1 is in, the vacuum LED flashes
during the pump wind-down period.
In this case, after the wind down
period, the blast gate closes and its
Australia's electronics magazine
LED goes off. If JP1 is out, the blast
gate and LED stay on, and the vacuum
wind-down period is bypassed.
Either way, it then goes back to the
initial state, checking for the appliance
or interlink signal to become active.
If, rather than the connected appliance switching on, the interlink signal
becomes active, all units other than
the one with the connected appliance
on will have their blast gate closed, if
not closed already. The blast gate LED
flashes during the closing period. Then
the blast gate LED switches off.
The vacuum and LED then switch
on, and stay on as long as the interlink signal remains active. When the
interlink signal goes off, the vacuum
motor is switched off. It then returns
to the initial waiting state.
Note that the state of the blast gate
is stored in non-volatile memory, so
the on/off setting for each blast gate is
restored on power-up. This does not
apply to when the blast gate was set
open manually via button S2.
Switching the vacuum on manually using switch S1 will cause the
master unit to switch on the vacuum.
The vacuum LED on the unit where
S1 was pressed will light but flash off
momentarily once per second to indicate manual mode. Automatic running
by interlink signal or appliance detection is disabled until the vacuum is
switched off via S1 on the unit that
initiated manual operation.
Manually opening the blast gate
on any unit does not affect automatic operation. When an appliance
switch-on is detected by one of the
units, the blast gates will be closed
for all units that did not detect an
appliance-on, and remain open or be
siliconchip.com.au
Fig.1: one control unit is required for each tool
that’s connected to the vacuum system. Two,
three or even more units can be linked together,
as shown here. Only the first unit connects to
the vacuum, and just the first (and the fourth,
if there are four to six)
requires the second mains
input. In use,
apply power to
the fourth unit
(ie. the second
mains input
unit) before
the first unit.
The blast gate
connections are
only required if
you’re
using a blast
gate system.
opened at the unit that detected the
appliance-on event.
Note that the timer periods are
determined by the Controller that has
detected the appliance that’s switched
on. If it is not the master unit, the vacuum run period is controlled via the
interlink signal from another unit.
This allows you to set different periods for each tool.
Circuit details
The circuit is shown in Fig.2. It is
in several sections; if you don’t want
blast gate control, that part of the circuit can be left off the PCB. Similarly,
if you just have a single tool to connect,
the interlinking section can be left out.
When a second or third unit is
built, they do not require the mains
power section to be populated. They
can instead receive 12V power from
the master unit. More than three units
can be joined, but one mains power
supply is required for every
three. Power is
interconnected using CON7 and CON8
via jumpers at JP2 and JP3.
If more than three units are connected, the supply must be broken
between the third and fourth unit by
leaving JP2 or JP3 out.
The master Vacuum Controller is
the only unit that requires the vacuum control section, comprising relay
RLY1, driving transistor Q1, diode D1,
the 1kW base resistor for Q1, the mains
power input and output connectors
(CON13/CON14) and fuse F2.
The Vacuum Controller is based
around microcontroller IC1. This
monitors the appliance current flow,
trimpot settings (VR1, VR2 & VR3),
switches S1 and S2, jumper selection
JP1 and the interlinking signal. It also
drives relays RLY1 & RLY2 for vacuum
and blast gate control, LED2 and LED3,
and the interlinking signal.
RLY1 and RLY2 are switched on
by the RC4 and RB7 outputs of IC1,
respectively. Both use 1kW current-
limiting series base resistors to drive
transistors Q1 and Q2. When a transistor is switched on, its collector goes
low, connecting one side of the relay
coil to ground. The 12V supply at the
other end of the coil powers the relay.
Diode D1 across RLY1’s coil, and
diode D2 for RLY2, quench the backEMF voltage from the coil when these
are switched off.
RLY1 is a single-pole, single-throw
(SPST) relay with 30A, 250V AC contacts to drive the vacuum. Mains active
from the vacuum IEC C14 mains input
power connector (CON13) is controlled via the relay contact to switch
mains outlet (CON14) power on or off.
RLY2, for blast gate control, is a 5A
double-pole, double-throw (DPDT)
relay. All its relay contacts are connected to screw terminals (CON5) and
to CON6, an RJ-45 connector. This
allows for an easy connection using
Cat 5 or Cat 6 cabling. A small adaptor
PCB can be used to convert the RJ-45
connections to 6-way screw terminals
at the other end, for wiring to the solenoid or actuator.
Current detection
Appliance current flow detection is
via the Active mains wiring between
the appliance input (CON11) and output (CON12); the Active wire passes
through current transformer T2. This
forms the primary winding for the current transformer. T2 produces an output current from its secondary winding that’s related to the current flow
through the mains Active wire.
The lid (shown left) requires holes for the three LED indicators and the
manual control switches. We have used fibre optic cable to transmit the light, as
the LEDs are mounted to the PCB.
siliconchip.com.au
Australia's electronics magazine
October 2025 57
The 10kW loading resistor gives
about 4V AC output with a tool current flow of 1A and the single pass of
the Active mains wire through the current transformer core.
While the input current to output
voltage for T2 is not very linear using
a 10kW loading resistance, we use this
high value to increase the sensitivity. A 100W loading resistor would be
used for measuring current more accurately. That would provide a more linear relationship, but sensitivity would
be reduced to only give 1V for a 10A
primary current with a single turn
through the transformer.
Since we are not interested in current reading accuracy, we use the
higher-sensitivity connection to detect
the appliance running current.
The startup current for the appliance
can be well over 20A, so the output
voltage from the current transformer
could be quite high (possibly around
80V). We limit this voltage using a
transient voltage suppressor (TVS1)
that clamps the voltage to about 13.8V
AC. This limits the current into the following op amp inputs to a safe level.
Voltage rectification
The output from T2 needs to be rectified to give a DC voltage suitable for
monitoring by microcontroller IC1.
A standard bridge rectifier requires
a signal greater than ±1.2V peak to
begin producing a rectified voltage.
Fig.3: the Blast Gate Adaptor circuit
(top) and wiring to use for a blast gate
with an actuator (bottom). With power
applied with the polarity shown, the
blast gate should close. You can test
this by switching on the 12V supply
with the controller off; if the blast gate
opens, reverse the connections.
58
Silicon Chip
A precision full-wave rectifier allows
the detection of voltage well below this
(down to a millivolt or less).
The rectification is done purely by
op amps (IC2a and IC2b), without the
aid of diodes. We have set the gain of
this precision rectifier to 1.5 times.
Rectifying the incoming AC voltage
without diodes is possible, provided
that the op amp has specific characteristics.
These include being able to operate
correctly (without output phase reversal) when a voltage is applied that’s
below its ground supply rail. In addition, the op amp must be able to pull
its output close to ground. If you are
interested in how this works in detail,
this is described in the section entitled
“Precision full-wave rectification”.
A 2.2kW resistor and 10μF capacitor filter the rectified waveform at the
output of IC2a to produce a smoothed
DC voltage suitable for IC1 to monitor
via its AN6 analog input and internal
analog-to-digital converter (ADC).
Trimpots VR1 to VR3 are used to
set time periods. VR1 sets the period
over which the vacuum runs after an
appliance is switched off. The voltage at VR1’s wiper determines the
time period, and can be set between
0V and 5V. This voltage is converted
to a digital value within IC1 using the
AN7 analog input that connects VR1’s
wiper to the ADC.
The VR1 setting gives a time period
ranging from about 0.5s when rotated
fully anti-clockwise through to 30s
when rotated fully clockwise.
Similarly, VR2 and VR3 can be
adjusted in voltage, but these settings
provide time period settings of 0-7.5
seconds. VR2 is the blast gate operation period (the time it takes the blast
gate to open or close fully). This determines when the vacuum starts after
detecting the appliance associated
with the blast gate starts up.
VR3 is for setting the vacuum wind
down period, the time the vacuum
takes to stop after being switched off.
We keep the blast gate open until the
vacuum has stopped running, whereupon the gate closes. There is an option
to keep this gate open when the appliance and vacuum stops and, in this
case, the wind down period can be set
to 0 (VR3 fully anti-clockwise).
The blast gate will close automatically when a different appliance runs
if there are more appliances and Vacuum Controllers all interlinked.
Australia's electronics magazine
Switches S1 and S2 are momentary
pushbutton switches connected to the
RA5 and RA4 digital inputs of IC1.
With the switches open, these inputs
on IC1 are pulled high via internal
pull-up currents. When a switch is
pressed, it pulls the input pin low,
close to 0V.
Blast gate wiring
The connection for a solenoid is
easy enough, with the common and
normally (NO) contacts used to switch
power to the solenoid when the relay
is energised.
Fig.3 shows how wiring is made for
an actuator. An actuator is essentially
a DC electric motor that drives a rod in
or out using a worm gear. The actuator
requires current flow in one direction
to open the actuator, by driving the
motor in one direction, and current
flow in the opposite direction, reversing the motor, to close the actuator.
Operating the actuator is achieved
using the DPDT relay contacts. The
actuator includes end-stop switches
that prevent the actuator from running
once it has reached its open or closed
limits. It is important when used with
our Vacuum Controller to wire the
actuator so that it opens the blast gate
when the relay is on, and closes the
blast gate when the relay is off.
Power supply
Power for the circuit is derived by a
mains transformer. This is connected
to the appliance power input IEC C14
connector (CON11) and fuse F1 via terminals CON1 & CON2.
Transformer T1 has two 9V AC outputs that are connected in parallel.
The output is rectified by bridge rectifier BR1 and filtered with two 470μF
capacitors to produce around 12V,
which powers the two relays. The 12V
is also applied to REG1, a 5V regulator, to supply IC1 and IC2. The transformer can deliver enough current to
run three of these circuits.
Only the master unit has the vacuum
control section, hence RLY1, so only
one such relay needs to be powered.
RLY2 (if used) for blast gate control is
only switched on in one of the Vacuum Controller units at a time. Since
the relays are the major current draw,
there isn’t much of an extra burden
when more units are attached.
The 12V power for the following
units is coupled via the interlinking
cable and JP2 (for CON7) or JP3 (for
siliconchip.com.au
Fig.2: the circuit mainly comprises microcontroller IC1, a currentsensing system comprising current transformer T2 and op amp IC2
(cyan dashed box), a basic mains power supply (red dashed box),
vacuum switching (mauve dashed box), blast gate switching (dark
blue dashed box) and interlinking components (green dashed box).
CON8). For the connection between
the third and fourth unit, where the
fourth unit has another mains power
supply, at least one of the power jumpers between these two units must be
left off to isolate the two separate 12V
supplies.
Interlinking
Transistor Q3 provides the interlinking feature. This transistor is driven
at its base via a 10kW resistor by IC1’s
RB5 output. When RB5 is taken high,
the transistor switches on, pulling
siliconchip.com.au
its collector low. With the
transistor off, the collector
is held high via the 10kW
pullup resistor.
The collector voltage is
the interlinking voltage.
Any transistor in any of the interconnected Vacuum Controller units can
pull this line low to indicate that their
appliance is running. When no transistors are on, then the interlink signal
is held high (5V) via the 10kW resistor
and any other 10kW resistors in other
interconnected units.
Australia's electronics magazine
In the unlikely event that more than
10 separate Vacuum Controller units
are interconnected, these resistors
should be increased in value, or some
left off, to keep the total parallel resistance at 1kW or higher.
When a unit detects its connected
appliance is on, it opens the connected
October 2025 59
blast gate. The low interlinking signal
causes the remaining blast gates associated with the remaining appliances
to be closed. This low interlink signal
will also indicate to the master unit
that the vacuum should run.
The units are interlinked using the
RJ-10 4P4C socket (or sockets) at CON7
and CON8. The first (master) and last
unit require one of these, while the
others all require both.
Construction options
Fig.4 shows the parts layout on
the main board. It is divided into the
same sections as the circuit diagrams,
with dashed boxes in corresponding
colours, since not all components
are necessarily required. The ‘core’
components outside these boxes are
required for all builds. For the master unit, the mains power (red) and
vacuum control (mauve) sections are
also required.
To use the blast gate option, the components in the dark blue box are also
required. Typically, CON6 is used so
that connection to the blast gate can
be made using a Cat 5 or Cat 6 cable,
suitable for handling up to 1A. If you
require more current, up to 5A, use
the CON5 screw terminals instead,
along with suitably rated wiring, passing through a cable gland in the case.
For secondary units, the mains
power section (red) isn’t required
unless you’re building more than three
units. Essentially, you’ll need to build
this section on every fourth unit.
Interlinking between units requires
only one RJ-10 socket (CON7 or CON8)
on the master or final unit. All others
(assuming there are more than two)
require both sockets. JP2 and JP3 are
used to connect the +12V power as
required.
Construction
The Vacuum Controller unit is built
on a double-sided, plated-through PCB
coded 10109251 that measures 151 ×
109mm. Most of the components are
installed on this PCB, and it is housed
within an IP65 enclosure measuring
171 × 121 × 55mm.
We’ll describe construction assuming everything is installed, so ignore
any components that are mentioned if
they don’t apply to your build. Start by
fitting the resistors. These have colourcoded bands, shown in the parts list,
but you should also use a digital multimeter to check each resistor before
mounting it.
Diodes D1 and D2 are next on the
list. Make sure these are orientated correctly before soldering their leads. BR1
can be installed, again with the correct
polarity, lining up the + printed on it
with the one on the PCB.
We used a socket for IC1, although it
could be soldered directly, assuming
it has already been programmed. Similarly, IC2 can be mounted on a socket
or directly onto the PCB.
Install the headers for JP1, JP2 and
JP3 next. Follow with the capacitors.
There are two types used: electrolytic
and MKT polyester. The electrolytic
capacitors need to be orientated correctly since they are polarised, with
their longer leads through the holes
marked with + symbols. The MKT
polyester capacitors can be installed
either way around.
REG1 mounts horizontally. Bend its
leads to suit the PCB holes and secure
its tab with an M3 screw and nut before
soldering the leads. Q1-Q3 can then be
fitted; they are all the same type; orientate them as shown in Fig.4.
CON1 to CON4 can now be installed.
Note that the wire entry for CON3 is
toward REG1; for CON4, the entry is
toward the lower edge of the PCB. Then
fit CON5-CON8. CON5 isn’t needed
if you intend to use CON6 instead.
CON5 allows for heavier-duty wiring
to the blast gate. The cable will need
to be secured to the side of the enclosure with a cable gland, or via circular
(8-way) audio connectors or similar.
Fig.4: follow
this overlay
diagram to
assemble
each control
board, but
note that some
boards may
not require the parts inside
each outlined section (for
example, the second and
third control boards in a
system don’t require the
mains power supply). The
colour coding of the dashed
sections corresponds to the
same sections in the circuit
diagram, Fig.2.
60
Silicon Chip
Australia's electronics magazine
siliconchip.com.au
Precision Full-Wave Rectification
We use a dual op amp to rectify the AC signal from the current
transformer, either an LMC6482AIN or MCP6272 (IC2). One stage
(IC2b) is connected as a unity gain-buffer, while the other (IC2a)
provides the 1.5 times gain. The points labelled A to E in Fig.2 correspond to the example waveforms shown here in Fig.a.
We’ll describe the operation using a 2V peak-to-peak sinewave
at point ‘A’. This makes the description easier since the sinewave
peaks at +1V and −1V. The rectification for the negative and positive waveforms are described separately.
For the negative half of the cycle, the signal applied to the
non-inverting pin 5 input of IC2b via the 15kW resistor will cause
the voltage at that pin (point B) to be clamped at around -0.3V due
to IC2b’s internal input protection diode. The output of IC2b (point
C) therefore sits at 0V during negative portions of the cycle, since
its output can’t go below the negative supply rail (0V).
IC2a adjusts its output (point E) so that the voltage at its inverting
input pin 2 (point D) matches the voltage at non-inverting input pin 3
(point C). Since pin 3 is at 0V, pin 2 will also be at 0V. Therefore, the
10kW resistor from point D to ground has no voltage across it, and it
plays no part in the circuit during the negative portions of the cycle.
With the 10kW resistor essentially out of the circuit, IC2a operates as a standard inverting amplifier with both inputs (points C
and D) at 0V. Its gain is therefore −30kW divided by 20kW, which
equals −1.5 times. So the −1V peak waveform is amplified and
inverted to produce +1.5V peak at point E.
With a positive voltage at the input (point A), the situation is
more complicated. Firstly, the voltage at pin 5 (point B) is reduced
below 1V peak due to the divider formed by the 15kW and 18kW
resistors. So the peak voltage becomes 0.5454V, ie, 1V × 18kW ÷
(15kW + 18kW).
Point C will also peak at 0.5454V, since IC2b is working as a unity-
gain buffer producing the same voltage at its output as its non-
inverting input. Once again, op amp IC2a adjusts the output voltage
(point E) so that the voltage at the inverting input at pin 2 (point
D) matches the voltage at the non-inverting input, pin 3 (point C).
To determine the resulting voltage, we calculate the currents
through the three resistors connected to point D. The current
through the 10kW resistor is waveform D voltage divided by 10kW,
which peaks at 54.54μA (0.5454V ÷ 10kW). The current through the
20kW resistor, with 1V peak at the input (point A), will be 22.73μA,
ie, (1V[A] − 0.5454V[D]) ÷ 20kW.
So we have 22.73μA flowing into the node at point D via the
20kW resistor and 54.54μA flowing away from that node via the
10kW resistor. The extra current of 31.81μA (54.54μA − 22.73μA)
to balance currents at node D needs to come via the 30kW resistor.
Remembering that voltage at point D peaks at 0.5454V, the
required voltage at point E is 1.5V, ie, 31.81μA × 30kW + 0.5454V.
So the circuit operates as a full-wave rectifier with a gain of 1.5.
The degree of precision depends on the op amp parameters and
resistor tolerances. The lower the offset voltage of the op amp
and the lower the op amp input bias current, the more accurate
the full-wave rectification will be, particularly at low signal levels.
We are not overly concerned with accuracy here. We just need
full-wave rectification of the incoming AC signal from the current
transformer that works down into the tens of millivolts range. A
standard diode-based rectifier would not give any output in this
case, due to the relatively large voltage drops across the diodes.
The scope output shows the operation of the full-wave rectifier
for a 1V peak (2V peak-to-peak) current waveform resulting from
an approximate 40W load through the appliance and current transformer. The waveform applied to the input of the full-wave rectifier (point A) is on channel 1 of the oscilloscope, shown in yellow.
Channel 2’s cyan waveform is the full-wave rectified waveform
(measured at point E). This is a 1.48V peak output waveform at
100Hz compared to 1V peak at 50Hz for the input sinewave. The
discrepancy of 20mV is due to tolerances in the resistors that are
only ±1% types, the op amp offset voltages, and the accuracy of
the oscilloscope readings.
The yellow trace is a 1V peak sinewave applied to point A in the
circuit (the input of the precision rectifier), while the cyan trace
is the output of the rectifier at point E. As expected, the negative
parts of the sinewave are flipped to be positive, allowing us to easily
measure the average current.
Fig.a: the expected waveforms at points A-E on the circuit (Fig.2)
for a 1V peak sinewave from current transformer T2. The output (E)
is a rectified version of the input (A) but 50% higher in amplitude.
siliconchip.com.au
Australia's electronics magazine
October 2025 61
The next step is to install the relay,
RLY1, with the coil terminals toward
CON3. The relay is secured using M4
machine screws and nuts, with each
screw inserted from the underside of
the PCB. RLY2 mounts directly on
the PCB.
Transformer T1 is a PCB-mounting
type; install it now. We use a cable
tie that wraps around the transformer
and through slots in the PCB to secure
the transformer. The cable tie is necessary to prevent the solder joints or
pins fracturing if the unit is dropped.
Current transformer T2 also needs
extra support for its mounting for
similar reasons. Apply glue to the
transformer base before inserting its
pins into the PCB and soldering it in
place. We used JB Weld epoxy resin,
since this adheres well to most types
of plastics.
The light
pipes are held together
over the LEDs when you lose the lid.
Blast gate PCB assembly
If using blast gate(s) with the RJ-45
socket option, you will probably want
Fig.6: the locations of cut-outs on
three sides of the case, plus the
dimensions of the IEC socket packing
piece and the light transporter
assembly jig. All the possible holes for
chassis-mounting connectors etc are
included, although some are optional.
62
Silicon Chip
Australia's electronics magazine
siliconchip.com.au
to build one of the Blast Gate Adaptor
PCBs for each gate. This converts the
RJ-45 8P8C connections to screw terminals. It is coded 10109252 and measures 44 × 33mm – see Fig.5. This can
be mounted near the blast gate actuator or relay.
Assembly is simple – just solder the
RJ-45 socket and screw terminals to
the board and it’s ready.
Final assembly
The Vacuum Controller units are
secured to the base of their enclosures
using M3 screws that go into the integral brass inserts. Before attaching the
PCB, cutouts are required for the IEC
C14 connectors at one end of the enclosure and the RJ-45 and RJ-10 socket(s)
at the other end.
The only hole that’s required in
every case is the IEC C14 connector
for the tool or appliance and its corresponding GPO cut-out; the other holes
are required only for those boards
where matching parts are fitted.
Start by drilling and shaping holes
using the template shown in Figs.6 &
7. The two IEC C14 connectors used on
the master unit have a shared mounting hole at the middle of the enclosure
end, where one connector is stacked
over the other.
The large cutouts for the mains
GPO and IEC C14 connectors can
be made by drilling a series of small
holes around the inside perimeter,
then knocking out the centre piece
and filing the job to a smooth finish.
Alternatively, use a speed bore drill to
remove the bulk of the central cut-out
area before filing it to shape.
For the master unit, a packing piece
needs to be fashioned so that the IEC
C14 connector that’s stacked over
the other can be spaced by the same
amount. We made ours from a piece
of 3mm-thick plastic cut from a discarded black UB1 Jiffy box.
Once the drilling and filing is complete, the PCB can then be placed
inside the case and secured with the
M3 screws into the integral brass
inserts. The IEC C14 connector(s)
must be secured using 15mm-long
M3 nylon screws, although metal nuts
can be used.
For the securing screws closest to
the edge of the enclosure, TO-220 insulating bushes can be used to space the
nut further out to avoid the nut from
angling inward against the enclosure’s
moulded curvature as it is tightened.
siliconchip.com.au
Fig.7: just five holes are required in the lid, as shown in this actual-size
diagram. You won’t need all five if you aren’t using the blast gate control option.
Using nylon screws prevents the
possibility of the screws becoming
live (at mains voltage) should a mains
wire inside the enclosure come adrift
and contact a screw that’s securing the
IEC connector.
The lid requires holes for the
switches and LED bezels of the light
transporters. Light transporters use
fibre-optic cable and plug-in connectors from the LED to the front panel
bezels. The fibre optic cables are cut
to length so that they connect without bending too much when the lid is
closed. This procedure can be done at
the end of construction.
Australia's electronics magazine
Fig.5: the Blast Gate Adaptor PCB is
dead simple; it just connects six of
the Cat 5/6 cable’s eight conductors to
screw terminals so they can be more
easily wired up to the blast gate. This
is suitable for gates that draw up to 1A.
October 2025 63
Fig.8: the two
versions of
the lid panel
artwork cater for
units built with
and without the
blast gate option.
There are also
some side labels
for connectors
that you might
like to use.
siliconchip.com.au
Fig.9: make sure to follow this wiring diagram carefully and only
use mains-rated wire. Don’t leave out the cable ties; they are not
just to keep it neat; they perform an important safety function
(preventing loose wires from contacting low-voltage circuitry).
It will be easier to install the lid and
attach the light transporters if a plastic
spacer is made to spread the LED connector clips 12.5mm apart. We made
ours from a 3mm-thick piece cut from
a discarded UB1 Jiffy box lid.
When installing the lid (later on),
it will be easier to make sure the light
transporters correctly line up and clip
over the LEDs when these are switched
on (via S1 and S2 if used) so you can
peep in through between the box and
lid as you close it.
There are two versions of the front
panel label artwork, depending on
whether the blast gate feature is used
or not. Labels for the mains inputs
and outputs and the interlinking and
blast gate connectors can be independently affixed to the side of the
enclosure, or on the side edge of the
siliconchip.com.au
lid as appropriate. The front panel
label shown in Fig.8 is available from
siliconchip.au/Shop/11/3002
Details on making a front panel from
this artwork can be found online at
siliconchip.au/Help/FrontPanels
Wiring it up
All wiring must be run as shown
in Fig.9, using mains-rated cable. Be
sure to use 10A cable where indicated
(for everything except RLY1’s coil and
switches S1 & S2). Brown wire is used
for Active, and blue wire for the Neutral leads. The green/yellow-striped
wire must be used for the Earth wiring only, and the Earth lead from each
IEC connector must go straight to the
corresponding GPO.
Insulate all the exposed connections
with heatshrink tubing for safety, and
Australia's electronics magazine
cable tie the wires to prevent any wire
breakages coming adrift. The Active
and Neutral leads are secured to the
GPO using a cable tie passing through
the hole in its moulding.
Use neutral-cure silicone sealant
(eg, Roof & Gutter Silicone) to cover
the Active bus piece at the rear of the
IEC connectors that joins the active
pin to the fuse.
Take great care when making the
connections to the mains socket (GPO),
ensuring you run the leads to their
correct terminals; each GPO will be
marked A (or L) for Active or Live,
N for Neutral and E for Earth. Do the
screws up tightly so that the leads are
held securely. Similarly, make sure
that the leads to the CON1 and CON2
screw terminals are firmly secured.
CON1 and CON2 are only required
October 2025 65
when the transformer (T1) is installed.
These screw terminals are there to connect the incoming mains to the transformer primary windings on the PCB.
Only one terminal of CON1 is used to
connect the Neutral. Similarly, one terminal of CON2 is used for the Active
connection.
Remove the spare terminal screw on
each terminal and use a mica washer
(normally used to insulate TO-220
transistors) as a cover for the used terminal. Secure it using an M3 × 12mm
nylon or polycarbonate screw with a
6.3mm nylon tapped standoff under
the washer through the hole where
you removed the metal screw.
Setting it up
If IC1 is already programmed, it can
be inserted into its socket now, taking
care to do so with the correct orientation. If IC1 is not yet programmed, do
that first. Programmed processors can
be ordered from our Online Shop. If
you have programming facilities, like
a PICkit and adaptor socket, the HEX
file is at siliconchip.au/Shop/6/3013
Set VR1 to the required vacuum run
time for after the appliance has been
switched off. The maximum is 30 seconds in the fully clockwise position.
It’s linear, so a halfway setting will
give you 15 seconds. Set VR2 to the
period that the blast gate takes to open
or close, or fully anti-clockwise if you
aren’t using that feature.
If the blast gate opening and closing
periods are different, set it to whichever is longer. The setting is 7.5 seconds when VR2 is fully clockwise.
Adjust VR3 for the wind-down
period that the vacuum takes to stop
after being switched off. As with VR2,
it will give 7.5 seconds when VR3 is
fully clockwise, or 3.75s at halfway.
When you have more than one unit,
the VR1, VR2 and VR3 settings are
used from whichever control unit that
detects the appliance switching on, so
you will need to set them all.
Indicator LEDs
The indicator LEDs will be either
flash, be fully on or off. The Power
LED is on when power is supplied
to the circuit. During the blast gate
opening/closing period, the blast gate
LED flashes and it remains lit while
the blast gate is open, switching off
when it closes.
The vacuum LED is continuously
lit while the vacuum is running on
66
Silicon Chip
Parts List – Vacuum Controller
Controller unit (common parts)
1 double-sided, plated-through 151 × 109mm PCB coded 10109251
1 171 × 121 × 55mm sealed ABS or PC enclosure [Altronics H0478, Jaycar HB6218]
1 AC1010 or AX1000 10A current transformer (T2) [RS Components 7754928, 1243903]
1 3-way, 5.08mm-pitch screw terminal block (CON4)
1 M205 10A fast blow fuse (F1)
1 2-way, 2.54mm-pitch pin header and jumper shunt (JP1)
1 SPST momentary pushbutton switch (S1) [Altronics S1084A, Jaycar SP0700]
1 IEC C14 mains input socket with fuse holder (CON11) [Altronics P8324, Jaycar PP4004]
1 side-entry 10A mains GPO socket (CON12) [Altronics P8241, Jaycar PS4094]
3 3mm LED light transporters [Jaycar HP1193; pack of 3]
1 LED fibre optic spreader made from 3mm plastic (see Fig.6 and text)
3 10kW miniature top-adjust trimpots (VR1-VR3)
1 20-pin DIL IC socket for IC1 (optional)
1 8-pin DIL IC socket for IC2 (optional)
Hardware and cable
1 150mm length of 7.5A mains-rated wire for S1
1 200mm length of blue 10A mains-rated wire
1 250mm length of brown 10A mains-rated wire
1 150mm length of green/yellow striped 10A mains-rated wire
1 40mm length of 5mm diameter blue or black heatshrink tubing
1 40mm length of 5mm diameter red or black heatshrink tubing
1 40mm length of 5mm diameter green heatshrink tubing
1 40mm length of 3mm diameter blue or black heatshrink tubing
1 40mm length of 3mm diameter red or black heatshrink tubing
2 M3 × 15mm nylon countersunk head screws
4 M3 × 6mm panhead screws
2 M3 hex nuts
1 TO-220 insulating bush
4 100mm-long cable ties
Semiconductors
1 PIC16F1459-I/P 8-bit microcontroller programmed with 1010925A.HEX, DIP-20 (IC1)
1 LMC6482AIN or MCP6272E/P dual CMOS op amp, DIP-8 (IC2) [Jaycar ZL3482]
1 7805 5V 1A linear regulator, TO-220 (REG1)
2 3mm red LEDs (LED1, LED2)
1 (P)4KE15CA 15V bidirectional TVS (TVS1) [Jaycar ZR1160]
Capacitors
1 470μF 16V PC electrolytic
2 10μF 16V PC electrolytic
1 100μF 16V PC electrolytic
2 100nF 63V or 100V MKT polyester
Resistors (all ¼W, 1% axial)
1 30kW
1 18kW
4 10kW
2 470W
1 20kW
1 15kW
1 2.2kW
Mains power supply parts
1 9 + 9V AC 3VA PCB-mounting mains transformer (T1) [Altronics M7018A]
2 PCB-mounting 8.25mm-pitch 300V 15A barrier screw terminals (CON1, CON2)
[Altronics P2101]
1 W04 bridge rectifier (BR1)
1 470μF 16V PC electrolytic capacitor
2 M3 × 12mm nylon or polycarbonate panhead machine screws
2 M3 × 6.3mm nylon tapped spacers
2 TO-220 mica insulating washers
1 150mm-long cable tie
Extra parts for master unit (besides mains power supply)
1 SPST 250V/30A 12V DC coil FRA4 relay (RLY1) [Jaycar SY4040]
1 2-way, 5.08mm-pitch screw terminal block (CON3)
1 IEC C14 mains socket with integral fuse holder (CON13)
[Altronics P8324, Jaycar PP4004]
1 side-entry 10A mains GPO socket (CON14) [Altronics P8241, Jaycar PS4094]
1 M205 10A fast blow fuse (F2)
1 BC337 45V 0.8A NPN transistor (Q1)
Australia's electronics magazine
siliconchip.com.au
1 1N4004 1A diode (D1)
1 1kW ¼W 1% axial resistor
1 200mm length of 7.5A mains-rated wire for the relay coil
1 200mm length of blue 10A mains-rated wire
1 250mm length of brown 10A mains-rated wire
1 150mm length of green/yellow 10A mains-rated wire
1 M3 × 15mm nylon panhead machine screw
1 M3 hex nut
1 TO-220 insulating bush
1 IEC mounting spacer made from 3mm-thick plastic (see Fig.6 and text)
11 100mm-long cable ties
Silicon Chip
Binders
REAL
VALUE AT
$21.50*
PLUS
P&P
Extra parts for blast gate control (per unit)
1 DPDT 5A PCB-mounting relay (RLY2)
[Altronics S4190D, Jaycar SY4052]
1 SPST momentary pushbutton switch (S2)
[Altronics S1084A, Jaycar SP0700]
1 RJ-45 8P8C side-entry PCB-mounting socket (CON6) [Altronics P1448A] •
1 BC337 45V 0.8A NPN transistor (Q2)
1 3mm red LED (LED3)
1 1N4004 400V 1A diode (D2)
1 1kW ¼W 1% axial resistor
1 470W ¼W 1% axial resistor
1 Cat 5 or Cat 6 cable (not crossover), length to suit installation •
1 Blast Gate Adaptor (see below) •
1 150mm length of 7.5A mains-rated wire for S2
2 100mm-long cable ties
• or replace these parts with 2 3-way, 5.08mm-pitch terminal blocks (CON5) and a cable gland
or chassis connector plus wiring to the blast gate for >1A
Interlinking two or more controller units (per pair of units)
1-2 RJ-10 4P4C side-entry PCB-mounting sockets (CON7, CON8) [Altronics P1442]
1-2 2-way, 2.54mm-pitch headers and jumper shunts (JP2, JP3)
1 4P4C handset (telephone) cord with RJ-10 connectors at each end; length to suit
1 BC337 45V 0.8A NPN transistor (Q3)
1 10kW ¼W 1% axial resistor
Blast Gate Adaptor (per adaptor)
1 double-sided, plated-through PCB coded 10109252, 44 × 33mm
2 3-way, 5.08mm-pitch screw terminal block (CON9)
1 RJ-45 8P8C side-entry PCB-mounting socket (CON10) [Altronics P1448A]
Keep your copies
safe, secure and
always available with
these handy binders
These binders will protect your
copies of Silicon Chip. They feature
heavy-board covers, hold 12 issues
& will look great on your bookshelf.
H 80mm internal width
H Silicon Chip logo printed in goldcoloured lettering on spine &
cover
Order online from www.
siliconchip.com.au/Shop/4
or call (02) 9939 3295
and quote your credit card
number.
*see website for delivery prices.
all units when powered, but flashes
on and off with an even duty cycle
once per second during the winddown period.
This LED also flashes momentarily off at the unit where the vacuum
is set to run manually using S1. This
indicates that manual mode was used,
and the vacuum needs to be switched
off using S1 to exit this mode before it
resumes automatic operation.
Don’t forget to set JP1 in each unit
as required. Leaving the jumper
link out will have the blast gate stay
open after opening. It will only close
if another Vacuum Controller unit
detects its appliance is on instead.
With the jumper link in, the blast
gate will close after the vacuum has
SC
stopped running.
siliconchip.com.au
Australia's electronics magazine
October 2025 67
|